WHAT: Pleasant Hill Public Safety Facility
WHERE: 6875 Martha L. Miller Drive, Pleasant Hill
PROJECT VALUE: $12 million
ARCHITECT: FEH Design PROJECT MANAGER: Ryan Cos.
BACKGROUND and UPDATE: Construction of a new public safety facility in Pleasant Hill is expected to be completed by late fall, city officials said.
The facility will house the eastern Polk County suburb’s police department. It will also include apparatus bays for the fire department.
The city’s current police headquarters will undergo a $4 million renovation to create a command center for the fire department.
According to an update provided to the City Council this month, interior slabs in the sally port drive and vestibule hallway are completed, plumbing has been roughed in, and masonry walls are being installed. Duct work is also being installed, according to a report from Ryan Cos.
– By Kathy A. Bolten
|